How Utilization for a Selected Task and Time Period is Determined (Gantt)

 

Utilization in the Gantt chart Sidebar is determined based on the time period of the selected task and, for each resource, the number of hours they are available to work.

This calculation takes into account the workweek calendar and any non-working time for the resource, as well as any hours they are currently assigned to tasks during that time period.