To add or edit a task's predecessors:
Note: If an error message displays, press Esc to dismiss the message and restore the previous Predecessors value.
Add a dependency type by specifying SS (start-to-start) or FF (finish-to-finish). The default dependency (FS - finish-to-start) is assumed if nothing is indicated and does not display even if you include it explicitly.
To specify a non-default dependency, type that immediately after the task number:
You can include a Lag (delay) or Lead (overlap) time for the dependency. Lag time is shown with positive numbers. Lead time is shown with negative numbers:
11FF+1
means that task 11 must finished before the current task can finish, and there is a 1 day lag after task 11 finishes before the current task can finish.
8-1
means there is a finish-to-start dependency (the default) between task 8 and the current task, and that 1 day before task 8 finishes, the current task will start.