About Tasks and Timesheets

 

In PPM, Tasks and Timesheets are linked, and interactions with one can affect data in the other. Values for Planned Work, Work to Date, Percent Complete, and ETC are consistent whether you are viewing the timesheet or the task details.

Updating a task (either using Timesheets, or from the task update) can affect Percent Complete and Actual Start and Finish dates. See About Task Percent Complete, Actual Start and Actual Finish for more information.

Note: If your organization tracks task work by updating tasks directly, you may not see a Timesheets tab. Check with your project manager or supervisor to find out how you should track project work.

When Tasks Appear on a Timesheet

Tasks display on your timesheet

When Tasks Do Not Appear on a Timesheet

Tasks will not display on your timesheet in these cases:

 

Note: For Workspaces that have workspace-level time tracking enabled, the Task Name column on Timesheets shows NA and tasks are not listed. For more information, see About Workspace-Level Time Tracking.

 