About the My Current Timesheet View
|
To take full advantage of the flexibility and power of the
Timesheets application, it is important to understand the various
screen elements of the application. The screen can be divided into 4 areas,
the Tab toolbar, the title section, the View toolbar, and the timesheet
content area.
Timesheet Tab Toolbar Options
- My
Current Timesheet—Use
this option to return to the My Current Timesheet view from any other
view in Timesheets.
- More
Views—Use
this option to switch between timesheet views. View options include:
- Export
Timesheets—Use
this option to:
- Export
the timesheet—export
timesheet data in Excel format (available based on the enterprise-role level
permission)
- Page
Options—Use
this option to:
Title Section
The title section includes the time period for the timesheet you are
viewing, as well as any options that are applicable, based on the status
of the timesheet and your relationship to the timesheet. For example,
if the timesheet has already been submitted for approval, Submit does not display.
View Toolbar Options
- Change
Time Period—Use
this option to quickly switch to a timesheet for a different time period. This allows you to switch to a timesheet from a prior time period, or to create and view a timesheet for a future period.
- Actions—Use this option
to:
- Page
Options—Use
this option to:
Content Area
- Workspaces—Workspace names
for tasks included in the timesheet.
- WBS—The work breakdown
structure indicates the relative position of the task in the schedule
and task hierarchy.
- Tasks—Names of tasks
included in the timesheet.
Note: For workspaces that have workspace-level time tracking enabled,
this field shows the workspace name and individual tasks
are not listed. For more information, see About
Workspace-Level Time Tracking.
- Status
icon—Indicates
the status of the task. Options are:
-
On
Hold (yellow)
-
Overdue
(red)
-
In
Progress (blue)
-
Not
Started (gray)
-
Complete
(green)
- NA
for workspaces using workspace-level time tracking.
- Task
Comments icon—Indicates
if there are comments associated with a task:
- A blank speech bubble icon means there are no task comments.
- A filled speech bubble icon means there are task comments.
- Planned
Work—The
estimated number of hours of work required to finish a task. If the task
has multiple assignees, all assignees
see the same value on their timesheets. Planned Work is the initial
estimate of the amount of work a task will take.
If the workspace is configured to automatically update
Planned Work with the Estimate to Complete (ETC) value, task Planned Work
automatically updates with ( + ETC) when a timesheet is approved.
Note:This
field is not applicable for non-project work and for workspaces where workspace-level
time tracking is enabled. For more information, see About
Workspace-Level Time Tracking.
- Work
to Date—The
total hours of work done on a task to date. This value is updated
dynamically when you add hours to your timesheet and includes approved hours (Actual Work) as well as hours entered on a timesheet but not yet approved.
This value is also updated
if you change the Total Hours Worked
field during a task update. For more information, see Updating
a Task.
Important:
If more than one person is assigned to a task, the Work to Date column
reflects work done by all assignees. This means you may see work listed
even if you have not yet added hours to the task.
Note: This
field is not applicable for workspaces where workspace-level time tracking
is enabled. For more information, see About Workspace-Level Time Tracking.
- %—The percent
of work that has been done on the task. If the task has multiple assignees,
all assignees see the same value on
their timesheets.
How this value is updated depends on whether or not
ETC is enabled for your enterprise:
- If ETC
is disabled, the % complete can be edited manually.
Note: This
field is not applicable for non-project work or when doing workspace-level
time tracking. For more information, see About
Workspace-Level Time Tracking.
- ETC—Estimate to
complete. This value is initially set for a task when the task is created,
but updates dynamically when hours are added or subtracted.
ETC is calculated using this formula:
ETC
= (Work to Date - ( (Percent Complete / 100) * work) ) / (Percent Complete
/ 100)
unless Work
to Date = 0 or Percent
Complete = 0. In these cases ETC is calculated using this formula:
ETC
= (Work to Date * ( (100 - Percent Complete) /
100) )
Note: This field is not applicable when
doing project-level time tracking or if your enterprise has disabled ETC.
For more information, see About
Workspace-Level Time Tracking and ETC Overview.
- Days
of the week—Fields
for entering hours of work done on a task.
- Totals—Timesheet
totals reflect hours worked by task (or project, when doing project-level
time tracking) and by day of the week. Totals are not updated until you
save your timesheet edits by clicking Save.
- Show
Totals for—This
list toggles the totals display between:
- Billable/Non-Billable
hours
- Project Work/Non-Project
Work
Related Topics: