Synchronizing Tasks

 

Synchronizing tasks is the process of ensuring that all tasks and task data in your Microsoft Project file and PPM project task schedule are the same. The following task data are synchronized: Task Name, Percent Complete, WBS number, Start Date, Finish Date and Assignees (resources).

There are two types of task synchronization:

Note: In most cases you begin using ProjectTransit with either an empty PPM schedule or an empty Microsoft Project file, and tasks are copied from the established schedule to the empty schedule. If you have tasks in both places they will be copied in both directions.

Important: You should only break schedule synchronization in specific circumstances. Be certain you understand the impact of ending a ProjectTransit schedule synchronization. For more information, see the Review Settings section.


Synchronization Summary

When a synchronization is complete, a Task Synchronization Summary screen displays. This screen lists all the tasks that have been added, deleted or updated in both your Microsoft Project file and in your PPM schedule.