Updating a Task From the Global Tasks Application
|
You can update your tasks from several places in PPM. This topic discusses updating tasks from the global Tasks application. For information on updating tasks from within a project, see Updating a Task from the Task List.
Task assignees can update tasks assigned to them, adding hours of work done on tasks, dates of that work and how much work is remaining to complete the task. Project managers can update tasks on behalf of external resources assigned to the tasks (external resources cannot log into PPM).
Note: To see the difference between updating a task and editing a task, see About Task Edit and Task Update.
When you update a task, an entry is created in the task update
history, accessible from the Update History tab
of the Task Detail window.
To update a task:
- Open the global Tasks application
- Click the Actions icon
next to the name of the task you want to edit, then click
Update Task.
Note: You can also click the task name to open the Task Details
window. For more information, see Using
the Item Details Window.
- If % Complete is editable,
in the % Complete box, type a number between
1 and 100 to represent
the percentage of the task work that is complete. Changing the % Complete
value may also change the Actual Start or Actual Finish date for the task.
For details, see About
Task Percent Complete.
Note:
% Complete is editable only if your enterprise uses % Complete to track task progress. For more information, see ETC
Overview.
- If you are a project manager,
and the task has an external resource assigned to it, an Enter Hours For list displays your
name and the names of all the external resources assigned to the task:
- To update the task
with work you did yourself, select your name.
- To update the task
for an external resource, select that resource name.
- In the
Hours Worked text box, type a number for the hours you worked on
the task, then type the date in the date box or click on the calendar
icon and select a date from the calendar.
Note: Entering hours worked can have the following
impacts:
- If your organization
uses both Tasks and Timesheets, any change you make to the Total
Hours Worked value is reflected immediately on your timesheet as
Work to Date but is not reflected on the
Task Details Actual Work until your timesheet
is approved.
- If your organization
tracks tasks using ETC, ETC is automatically decremented by the number
of hours entered in Total Hours Worked, and % Complete is automatically incremented
based on the amount of work performed and the amount of work remaining.
See calculations (see Percent
Complete Calculations).
- For projects with Task ETC auto-update enabled, if exceeds Planned Work, the value for Planned Work will be updated to the new Actual Work value. If you need to view how actual work is impacting (or exceeding) your planned work, you can create baselines to track the values over time. See Baseline Overview for more information. For more details on Task ETC auto-update, see About Task ETC Auto-Update.
- If you know the date that
work on the task started or finished, type a date in the Actual Start or Actual
Finish boxes, or click the calendar icon and select the date from
the calendar.
Note:
If Actual Start or Actual Finish is blank, and you change
% Complete, this can change the Actual Start and
Finish dates.
- In the Update
Notes box, type any additional information about the task update.
- With proper permission you can edit or delete a previous work entry for the task in the Hours Worked per Day section.
- In the Notificationssection, select team members to notify
that the task has been updated.
Click Browse Member Directory
to open the User Selector and select team members to notify.
- If you want to include
a custom notification message, select Type
Custom Notification Message and type the message in the Notification Message box.
- Click Save or Save
& Add Another to update the task or Cancel
to close the window without updating the task.
Related
Topics: